History of Work Completed to Improve and Maintain Tank Tower

Maintaining Owner Investment is important to the Body Corporate Committee as demonstrated by these activities:

2023

  • Street facing podium level painting

  • Walls surrounding the pool painting

  • Paint patch repairs

2022

  • Ventilation improvements to prevent water ingress

  • Level 18 box gutter and overflow improvements

  • Level 5 common area waterproofing & tiling 

  • Lobby lighting repairs & intercom repairs

2021

  • Energy efficient pool heater & pool cover

  • Driveway entrance painting & presentation

  • Level 18 roof repairs & downpipe improvements

2020

  • Street entrance renewal & painting

  • L5 Recreation Area project including waterproofing, tiling, enclosing from weather and renovation

  • Fire compliance items and Certificate of Classification

  • Street image improvements

2019​

  • Waterproofing membrane and tiling of 502&503 Podiums

  • Tower & area under pool waterproofing

  • Fire compliance items

  • Pool glass barrier installation

  • Painting front balconies, render repairs and carpark walls

2018

  • Lift Lobby painting and light fittings

  • Waterproofing membrane and tiling of 501 Podium

  • Fire compliance items

  • Storage area cleanup - under ramp, under pool, etc

2017

  • Lift Security Integration

  • Automatic Opening Front Door

2016

  • Window Rectification Project 

  • Fire Audit 

  • Structural column repairs

  • NBN Fiber Optic for fastest internet speeds

  • Engaged with BCC to fix multiple streetscape items including:

    • Garden bed located at Tank St end of Kurilpa Bridge (complete)

    • Bent pole at Bench Cafe

    • Light pole at Bench Cafe
       

2015

  • Replacement Pool Heater (at no cost to the Body Corporate)

  • Brisbane City Council complaint regarding neighbouring fan noise

  • Replacement Intercom

  • Gym TV replacement, new Full Length Mirrors

  • Upgraded Security and additional cameras

  • Driveway pavement repair & new footpath lighting

  • Driveway mirror repair and new bollards

  • Levels 1-4 Lift Lobby Painting

  • Box Gutter replacement

  • Guard rail repairs

  • Tiling repairs

  • Nov 2014 storm damage repairs

    • Window Glass replacement

    • Awning replacement

    • Downpipe replacement

    • Downpipe painting

  • Balcony concrete, water ingress & plumbing repairs 
     

2014

  • Fire Certification & Safety

  • Ground Level Entrance Lobby Renovation

  • Level 5 Lift Lobby Tiling

  • Level 5 Common Area Intense Cleaning (Gym & other facilities)

  • Disabled Access facilities (Level 3)

  • Window Investigation and Report

  • Other safety work including abseil anchor points